The target for this week was to install and commission the wood burning stove; this required the installation of the hearth, stove, flue liner and cowl. This was all successfully completed in a day and the stove is operational for space heating. The back boiler unit will be fitted when the heat store unit is installed.
We also completed the platform in the roof space and installed a temporary hot water cylinder, this is to be used when the existing boiler is removed and the heat store installed.
The floor insulation to the living room floor was completed this week as well as the flooring in the under stairs cupboard, there now remains the bathroom to tackle.